Hut 8 Reports Major Equipment Failures At Drumheller Facility

Hut 8 Mining (TSX: HUT) continues to experience operating difficulties at its Drumheller, Alberta facility. The firm is said to be operating at just 15% of its installed hashrate at the facility as a result of equipment failures.

The problems at the Drumheller facility are said to be related to high energy input levels that caused the equipment failures, with the company hiring more staff to enable faster repairs on the equipment. Repairs are said to currently be underway, with firmware being installed to reduce maximum output voltages in an effort to correct the problem.

“We are very aware of the impact that the issues at Drumheller are having on the broader business: they are complex and challenging, but we have made meaningful progress and have a roadmap to remediation,” commented Hut 8’s CEO Jamie Leverton.

READ: Hut 8 Mining To Combine With US Bitcoin Corp, Abandons HODL Strategy

The Drumheller facility is also said to be experiencing elevated energy prices, creating further headwinds, while the company looks for a means to place the 7,000 miners removed from its North Bay, Ontario facility back into operation.

Equipment failures were first noted to have occurred in February, with production being heavily impacted in the time since.

The struggles with the facility resulted in just 132 bitcoin being produced during the month of April, a decline from the 188 produced in January, and the 156 produced in February. The figure was a slight improvement however from the 131 bitcoin produced in March.

The installed hashrate at the end of the month meanwhile sat at 2.6 EH/s, while Hut 8’s balance of unencumbered bitcoin sits at 9,265.

Hut 8 Mining last traded at $2.40 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Leave a Reply

Video Articles

Bell Q3 Earnings: Massive Impairments. Guidance Cuts. A Mess.

Alamos Gold Q3: Record Revenue & Production Amid Rising Costs

The Junior Mining Market Is Back

Recommended

Germany Looks To Modernize Military Recruitment But Stops Short of Conscription

First Majestic Silver Posts Topline Revenue Of $146.1 Million In Q3 2024

Related News

Hut 8 Mining Conducts $77.5 Million Financing

Money continues to flow into the cryptocurrency sector this morning, with Hut 8 Mining Corp...

Monday, January 11, 2021, 07:34:04 AM

Hut 8 Sees Equipment Fail At Drumheller Facility As Fast As It Can Be Repaired

Hut 8 Mining (TSX: HUT) appears to be keeping its operation moving along as a...

Friday, June 9, 2023, 09:03:56 AM

Hut 8 Mining Announces US$65 Million ATM Financing Months After US$173 Million Raise

Hut 8 Mining (TSX: HUT) last night attempted to quietly announce that it will be...

Saturday, February 12, 2022, 11:51:34 AM

Hut 8 Mining: Pressured By Declining Revenue And Rising Costs

Hut 8 Mining Corp (TSX: HUT), one of the largest publicly traded Bitcoin miners in...

Wednesday, September 30, 2020, 06:45:00 PM

Hut 8 Mining: Canaccord Halves Price Target To US$6.00

On May 12th, Hut 8 Mining (TSX: HUT) reported its first quarter financial results. The...