Hut 8 Reports 107 BTC Produced In June

Hut 8 Corp (TSX: HUT) saw the production of 107 bitcoin during the month of June under its self-mining operations, a dramatic 17.6% increase from the 91 produced in May.

The bitcoin production increase followed the company increasing its deployed hashrate from 5.5 EH/s to that of 5.7 EH/s, as detailed in the firms June production update released last night. Hut 8’s total hashrate under management meanwhile improved from 17.3 EH/s to 17.8 EH/s, with half of that growth coming from managed services.

Total energy capacity under management meanwhile remained flat from May to June, with that figure currently sitting at 762 MW.

The production increase resulted in the firms bitcoin holdings improve by two bitcoin to 9,105 BTC.

“We continue to optimize our existing assets, including our self-mining sites and five high performance computing data centers, for Bitcoin mining or AI workloads,” commented CEO Asher Genoot.

READ: Hut 8 Announces $150 Million Investment from Coatue Management In A Bid For AI Shift

Outside of bitcoin mining, Hut 8 reportedly is progressing in its artificial intelligence vertical, with over half of its purchased Nvidia GPU’s having been configured and now undergoing testing. The vertical is expected to go live in the second half in the year, with annualized revenue from the segment currently forecast to hit $20 million.

Hut 8 Corp last traded at $21.53 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Hut 8 Announces $150 Million Investment from Coatue Management In A Bid For AI Shift

June 24, 2024, 04:30:00 PM

Hut 8 Corp Sees Self-Mining Bitcoin Production Fall 21% In March

April 5, 2024, 09:54:50 AM

Hut 8 Closes Drumheller Mining Facility Despite Bitcoin Price Momentum

March 6, 2024, 08:28:58 AM

Hut 8 Changes Strategy, Bitcoin Now To Be Used To Fund Growth

February 27, 2024, 09:19:38 AM

Hut 8 Replaces CEO With Co-Founder Of US Bitcoin Corp

February 7, 2024, 09:52:59 AM

Hut 8 Corp Loses Managed Service Capacity After Marathon Digital Site Purchase

February 2, 2024, 09:31:53 AM

Hut 8 Mining Mines 58% Less Bitcoin In Q2 2023

August 14, 2023, 02:16:00 PM

Hut 8 Sees Equipment Fail At Drumheller Facility As Fast As It Can Be Repaired

June 9, 2023, 09:03:56 AM

Hut 8 Reports Major Equipment Failures At Drumheller Facility

May 9, 2023, 08:47:04 AM

Hut 8 Mining To Combine With US Bitcoin Corp, Abandons HODL Strategy

February 7, 2023, 08:17:11 AM

Hut 8 Mining Takes North Bay Facility Dispute To Court

January 26, 2023, 08:10:42 AM

Hut 8 Sees Bitcoin Mining Fall 32% In December As Production Slump Continues

January 6, 2023, 08:30:47 AM
Video Articles

Bell Q3 Earnings: Massive Impairments. Guidance Cuts. A Mess.

Alamos Gold Q3: Record Revenue & Production Amid Rising Costs

The Junior Mining Market Is Back

Recommended

Germany Looks To Modernize Military Recruitment But Stops Short of Conscription

First Majestic Silver Posts Topline Revenue Of $146.1 Million In Q3 2024