Ivanhoe Mines Hits Commercial Production At Phase 3 Concentrator At Kamoa-Kakula Copper Complex

Ivanhoe Mines (TSX: IVN) has achieved commercial production at its phase three concentrator at the Kamoa-Kakula Copper Complex in the Democratic Republic of the Congo. The addition of the third phase concentrator is expected to increase annual copper production capacity to over 600,000 tonnes at the complex.

Production at the phase three concentrator began on June 10, following the phase being completed ahead of schedule in late May. The concentrator is said to now be operating at the nameplate processing capacity of 5 million tonnes of ore per annum, while also exceeding capacity by as much as 19% on multiple occasions within a 24 hour window.

With the concentrator now in commercial production, the Complex reportedly produced 35,941 tonnes of copper in July. Presently, Ivanhoe is focused on improving recovery rates, with fine-grinding mills currently being installed that will increase recovery at the third phase concentrator from 80% to nameplate capacity of 86%. Engineering meanwhile is expected to begin soon to find a means to increase recovery beyond 90%.

Silver47 Exploration Inc. — sponsored Sponsored · Silver47 Exploration Inc.

The achievement however is overshadowed by a fatality that occurred on site last week, which was announced Friday evening. An employee operating an underground drill rig at the Kansoko mine was struck by a fall of ground, and later succumbed to their injuries at hospital. An investigation into the matter is said to be ongoing.

Ivanhoe Mines last traded at $17.26 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to the organizations discussed. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

Silver Is in a New Price Regime, and the Market Isn’t Used to It | Keith Neumeyer – First Majestic

Agnico Eagle Just Made a Massive Gold Land Grab

A Copper-Gold Deposit Caught the White House’s Attention | Rob McLeod – Cambria Gold

Recommended

Mercado Drills 256 g/t Silver Over 6.5 Metres In First Drill Hole of Inaugural Program

Antimony Resources Drills 4.38% Sb Over 7.05 Metres At Bald Hill In Final Hole Of 2025 Program

Trending

Related News

Ivanhoe Mines Begins Copper Anode Production At Kamoa-Kakula Smelter

Ivanhoe Mines (TSX: IVN) is reporting that the first copper anodes were produced this week...

Friday, January 2, 2026, 09:18:53 AM

Congo Bans Copper and Cobalt Exports Following Ivanhoe Mines Project Debut

The Democratic Republic of Congo (DRC) has once again banned exports of of copper and...

Saturday, May 29, 2021, 11:22:00 AM

Ivanhoe Mines Slashes Output Guidance, Q2 2025 Profit Drops 48%

Ivanhoe Mines (TSX: IVN) delivered a bruising second-quarter that pairs record throughput at Kamoa-Kakula with...

Thursday, July 31, 2025, 08:20:23 AM

Ivanhoe Sees Q3 Copper Production Fall To 71,266 Tonnes At Kamoa-Kakula

The third quarter saw copper production drop to 71,266 tonnes at Ivanhoe Mines’ (TSX: IVN)...

Tuesday, October 7, 2025, 09:26:59 AM

Ivanhoe Mines Strikes Deal With Zambia to Kickstart Copper Exploration

Zambia, already renowned for its abundant copper resources, has taken a significant step toward advancing...

Tuesday, September 10, 2024, 10:36:00 AM